As I have previously reported, during the summer of 2023, an engineer’s study was conducted on the overall health and status of Sewer District #1 in Huletts Landing. After more than 2 years, the final report still has not been completed.
However, in the last week the Town has released a new updated unfinalized report detailing what the engineer’s report shows at this time. It is posted on the Town’s website here. It is still not final.
So this document contains the most recent response from the engineering firm in the ongoing comment period with the NYS Environmental Facilities Corp, grantor of the Engineering Planning Grant that paid for the system study of Sewer District #1. EFC acknowledged receipt on 10/17/25 and EFC will review this latest round of responses.
There is no response window deadline for the state. We continue to wait for the final report but thanks to the Town for releasing this now to show where the process presently stands.